Kick-off  LIFE VERTALIM Project LIFE15 ENV/ES/000373, in the collector network of  ONDARROA WWTP. Dossier Nº 2234. Led by CABB

Last Thursday, May 10, 2018, a field visit was made to start the second stage of the Project with Dinalan (leader in the telecommunications engineering sector) through the Public Bidding-Contest process. Dinalan has established an agreement with HACH-LANGE for the supply of measuring equipment and ENERTEC for the electrical installation.

The works will consist of the supply, installation and connection of different instrumentation in the WWTP of Ondarroa, in the industrial WWTP of four canneries, and in the outlet to the collector of the Gardotza industrial area, in addition to its integration in the control and visualization system in the SCADA of the Ondarroa WWTP and the Galindo WWTP within phase B2.2 of the Project.

ogether they made the visit to the area of ​​implementation of the project before starting work on:

  • Detailed setting-out.
  • Equipment and location,
  • Manufacture of electrical panels.
  • Continuation of the Iberdrola’s request processing for the connection of  electrical cabinet in Gardotza industrial area. The existing pipes are detailed..
  • Start of the Works for the placement of conductivity probes, TOC analyzer and pH probes.
  • Establishment of the roadmap for projected works and schedule for orders of the instrumentation.